# DOTHAN WAREHOUSE INVESTORS, LLC D/B/A DOTHAN WAREHOUSE
> **Administrative - Formal** · FY2022 · — · Final Order With Penalty
## Case
- **Activity ID:** `3603510592`
- **Case Number:** 04-2022-0214
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- DOTHAN WAREHOUSE (complaint) (settlement)
- DOTHAN WAREHOUSE INVESTORS, LLC D/B/A (complaint) (settlement)
## Summary

1/19/2023 - EXPEDITED SETTLEMENT AGREEMENT ISSUED ASSESSING A PENALTY OF $1,620. PENALTY DUE WITHIN 15 DAYS.

ALLEGED VIOLATIONS: 
BASED ON A COMPLIANCE MONITORING INSPECTION CONDUCTED ON MARCH 01, 2022, THE EPA ALLEGES THAT THE RESPONDENT VIOLATED THE ACT?S SECTION 112(R)(7), CHEMICAL ACCIDENT PREVENTION
PROVISIONS, 42 U.S.C. ? 7412(R)(7), WHEN AT THE TIME OF INSPECTION, RESPONDENT DID NOT PROVIDE EVIDENCE THAT:
- IT DOCUMENTED THAT EQUIPMENT COMPLIES WITH RECOGNIZED AND GENERALLY ACCEPTED GOOD ENGINEERING PRACTICES AS REQUIRED BY 40 C.F.R. ? 68.65(D)(2) DUE TO FROST BUILD-UP OBSERVED AROUND PIPING IN THE ENGINE ROOM REGARDING ANSI/IIAR 2-2014 SECTION 5.10.1.
- THE INSPECTION AND TESTING PROCEDURES FOLLOWED RECOGNIZED AND GENERALLY ACCEPTED GOOD ENGINEERING PRACTICES AS REQUIRED BY 40 C.F.R. ? 68.73(D)(2), DUE TO PEELING PAINT ON AMMONIA PIPING WHICH COULD LEAD TO CORROSION AND PITTING.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*