# MISSOURI MACHINE AND PLOW, LLC
> **Administrative - Formal** · FY2022 · — · Final Order With Penalty
## Case
- **Activity ID:** `3603553151`
- **Case Number:** 04-2022-0303
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- MISSOURI MACHINE AND PLOW, LLC (complaint) (settlement)
## Summary

FEBRUARY 15, 2023 - Expedited Settlement Agreement and Final Order 

On10/21/2021,  representatives  of  the  EPA  inspected  the Respondent?s facility at 807 West Ave, Cedartown, GA 30125 (Site). Observations indicated operations at the facility were responsible for allegedly discharging industrial stormwater without a permit at the Site.

Based on information obtained during the EPA inspection, the EPA finds that: (1) Respondent, who is the operator of the Site, discharged  industrial  stormwater  from  the  Site  without authorization by any permit issued pursuant to the Clean Water Act (Act) in violation of Section 301 of the Act, 33 U.S.C. ? 1311]; (2) Respondent is a ?person? as defined in Section 502(5) of the  Act, 33 U.S.C. ? 1362(5); and (3) Respondent is responsible for the alleged violations specified in the attached  Industrial Stormwater Non-Filer Inspection Findings, Alleged Violations, and Proposed Penalty Form  (Alleged Violations Form). The Alleged Violations Form is hereby incorporated into this Agreement by reference.

The EPA also finds, and Respondent admits, that the EPA has jurisdiction over this matter pursuant to Section 309(g) of the Act, 33 U.S.C. ? 1319(g). Respondent neither admits nor denies the factual allegations alleged in the Alleged Violations Form.

The EPA is authorized to enter into this Agreement under the authority vested in the Administrator by Section 309(g) of the, 33 U.S.C. ? 1319(g), and by ?? 40 C.F.R. ? 22.13(b) and 22.1

---