Summary

On 6/1/23, EPA Region 6 issued an Expedited Settlement Agreement and Final Order (ESAFO) under its authority pursuant to the Toxic Substances Control Act to CB Builder / Clyde Beaty Homes, Inc. located in Tyler, Texas. The ESAFO was issued in response to violations of the Lead Paint Renovation Repair and Painting Rule in 40 C.F.R. section 745. The ESAFO requires CB Builder / Clyde Beaty Homes, Inc. to return to compliance and pay a penalty of $2,000.