# NORTHEAST CHURCH ROCK MINE SITE AND UNITED NUCLEAR CORPORATION MILL SITE PRE-REFERRAL NEGOTIATION
> **Judicial** · FY2023 · — · Final Order With Unspecified Cost Recovery
## Case
- **Activity ID:** `3603720481`
- **Case Number:** 09-2023-2501
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Unspecified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- GENERAL ELECTRIC (complaint) (settlement)
- UNITED NUCLEAR CORPORATION (complaint) (settlement)
## Summary

The CD is for the reimbursement of costs incurred by the USEPA and the Department of Justice (?DOJ?) for response actions at the Northeast Church Rock Mine Site (?NECR Site?) and the United Nuclear Corporation Site, and performance of work by the by the defendants at the Sites.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*