# CENTRAL COUNTIES COOPERATIVE (ATWATER, MN) - ESA
> **Administrative - Formal** · FY2024 · — · Final Order With Penalty
## Case
- **Activity ID:** `3603855221`
- **Case Number:** 05-2024-5013
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- CENTRAL COUNTIES COOPERATIVE (complaint) (settlement)
## Summary

This was a late filer that submitted their RMP 215 days late. Document was sent to the company for notice and agreement on December 14, 2023. The company has 30 days to respond. Company responded with note that they had issues with a misunderstanding by the company on cdx requirements.

---