Administrative - Formal · FY2024 · — · Final Order With Penalty · 3603923337

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2024-3308
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

This Consent Agreement and Final Order memorializes a settlement regarding Clean Water Act violations associated with the Respondent's Municipal Separate Storm Sewer System. Respondent has agreed to pay a civil penalty in the amount of $15,600 and will complete a Supplemental Environmental Project which consists of a rain garden at a cost of $27,080.