← EPA enforcement cases

DELAWARE DEPARTMENT OF TRANSPORTATION (ELKTON)

Administrative - Formal · FY2024 · — · Final Order With Penalty · 3603925237

Penalty
Cost recovery
Compliance action

Case

Case Number
03-2024-0003
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On March 12, 2024, the Division Director of ECAD, EPA R3 issued a Consent Agreement and Final Order ( CAFO ) under Section 309(a) of the Clean Water Act ( CWA or Act ), 33 U.S.C. 1319(a), to Delaware Department of Transportation (DelDOT) for violations of its National Pollutant Discharge Elimination System (NPDES) permit under the General Permit Authorization for Discharges from Construction Activities in Delaware (NPDES Permit No. 0051268). The violations were discovered during June 2019 inspections at four different construction sites: Elkton Road, a 38-acre site located at Elkton Road and Casho Mill Road (roadway reconstruction and expansion); Mulberry, a 12-acre site located at Mulberry Knoll Road to Lexus Way (expansion to 4-lane road); Georgetown, a 22.8 acre site located at the intersection of Sand Hill Road and Market Street on Route 9 (pavement rehab and road widening); and Claymont, a 3.8-acre site located at the Claymont Regional Transportation Center (construction of roadway entry). Violations include: 1) failure to post a notice of coverage under the permit; 2) failure to properly maintain stormwater controls; 3) failure to properly implement erosion and sediment control requirements; 4) failure to properly implement pollution prevention requirements; and 5) an incomplete stormwater pollution prevention plan. These failures constitute a violation of Section 301(a) of the CWA, 33 U.S.C. 1311(a), and of the NPDES General Permit for Discharges of Stormwater fr

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown