← EPA enforcement cases

TAYLOR FARMS TENNESSEE, INC

Administrative - Formal · FY2024 · — · Final Order With Penalty · 3604089119

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2024-0310
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

8/21/2024 - CONSENT AGREEMENT FINAL ORDER ISSUED ASSESSING A PENALTY OF $41,432. PENALTY DUE WITHIN 30 DAYS UPON RECEIPT OF THE EXECUTED ESA. ALLEGED VIOLATIONS: ON JULY 31, 2023, MARCH 14, 2024, AND APRIL 16, 2024, REPRESENTATIVES OF RESPONDENT AND THE EPA HELD A MEETING TO DISCUSS THE NOPVOC ISSUED BY EPA TO THE RESPONDENT ON FEBRUARY 15, 2023. ON AUGUST 23, 2022, THE EPA CONDUCTED AN ON-SITE INSPECTION OF RESPONDENT?S RMPROGRAM RELATED RECORDS, EQUIPMENT, AND PROCESSES. BASED ON EPA?S COMPLIANCE MONITORING INVESTIGATION, THE EPA ALLEGES THAT THE RESPONDENT VIOLATED 40 C.F.R. PART 68, THE CODIFIED RULES GOVERNING THE ACT?S CHEMICAL ACCIDENT PREVENTION PROVISIONS AND SECTION 112(R) OF THE ACT, 42 U.S.C. ? 7412(R), WHEN IT: A. FAILED TO DOCUMENT THAT EQUIPMENT COMPLIES WITH RAGAGEP, AS REQUIRED BY 40 C.F.R. ? 68.65(D)(2); B. FAILED TO FOLLOW RAGAGEP FOR INSPECTION AND TESTING PROCEDURES, AS REQUIRED BY 40 C.F.R. ? 68.73(D)(2); AND C. FAILED TO DOCUMENT EACH INSPECTION AND TEST THAT HAS BEEN PERFORMED ON PROCESS EQUIPMENT. THE DOCUMENTATION SHALL IDENTIFY THE DATE OF THE INSPECTION OR TEST, THE NAME OF THE PERSON WHO PERFORMED THE INSPECTION OR TEST, THE SERIAL NUMBER OR OTHER IDENTIFIER OF THE EQUIPMENT ON WHICH THE INSPECTION OR TEST WAS PERFORMED, A DESCRIPTION OF THE INSPECTION OR TEST PERFORMED, AND THE RESULTS OF THE INSPECTION OR TEST AS REQUIRED BY 40 C.F.R. ? 68.73(D)(4).

Source

Authoritative
EPA ECHO
Machine