← EPA enforcement cases

East Vacuum Liquide Recovery Plant/CO2 Plant-Lovington, NM-RMP ESA-FY 2025

Administrative - Formal · FY2025 · — · Final Order With Penalty · 3604294748

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2025-3323
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On July 5, 2024, EPA Risk Management Program Reporting Center sent a letter to Respondent, notifying Respondent of its failure to update the Risk Management Plan on file with the EPA for its facility located in Buckeye, NM (the ?Facility?). Facilities subject to the Risk Management Program (RMP) regulations at 40 C.F.R. Part 68 are required to submit an updated Risk Management Plan at least once every five years. EPA?s review indicates that the update for the facility was not submitted by the required due date of June 12, 2024.