JBS - Cactus Beef Processing Facility-Cactus, TX-RMP ESA-FY 2025

Administrative - Formal · FY2025 · — · Final Order With Penalty · 3604402592

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2025-3346
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On March 7, 2022, EPA Risk Management Program Reporting Center sent a letter to Respondent, notifying Respondent of its failure to update the Risk Management Plan on file with the EPA for its facility located in Cactus, TX. The EPA?s review indicates that the update for the facility was not submitted by the required due date of February 13, 2022.