# James Lake Gas Plant-Goldsmith, TX-RMP ESA-FY 2025
> **Administrative - Formal** · FY2025 · — · Final Order With Penalty
## Case
- **Activity ID:** `3604425958`
- **Case Number:** 06-2025-3390
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- James Lake Gas Plant (complaint) (settlement)
## Summary

On July 5, 2024 EPA RMP Reporting Center sent a letter to Respondent, notifying Respondent of its failure to update the RMP on file with EPA for the Facility. EPA conducted an investigation of the Facility on May 12, 2025, to determine Respondent's compliance with Section 112(r) of the CAA, 42 U.S.C. ? 7412(r), and 40 C.F.R. Part 68 (the  Investigation ).Based upon the information gathered during the Investigation, EPA determined that the Respondent violated certain provisions of the CAA.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*