← EPA enforcement cases

Weston County Mallo Camp

Administrative - Formal · FY2025 · — · Final Order No Penalty · 3604451583

Penalty
Cost recovery
Compliance action

Case

Case Number
08-2025-0114
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

The Order addressed several alleged violations identified from the year of 2023 and 2024. Violations include failure to complete seasonal startup procedures in 2023 and 2024 and failure to monitor for total coliform during September 2024. The Order requires the Respondents to complete the seasonal startup checklist; monitor the System?s water for total coliform; and notify the public of the violations. The Water Division provided the System extensive compliance assistance prior to the SDWA Enforcement Section initiating this enforcement action. The System serves approximately 317 individuals at least 60 days a year.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown