← EPA enforcement cases

SHERBORN MS4

Administrative - Formal · FY2025 · — · Final Order No Penalty · 3604467253

Penalty
Cost recovery
Compliance action

Case

Case Number
01-2025-2076
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

On July 24, 2025, the Region issued Administrative Compliance Orders to the Town of Pembroke (Docket No. CWA-AO-R01-FY25-74) and the Town of Sherborn (Docket No. CWA-AO-R01-FY25-74) for their respective violations of the 2016 General Permit for Stormwater Discharges from Small Municipal Separate Storm Sewer Systems in Massachusetts (2016 MS4 Permit). The Orders cite their failure to develop or modify, as appropriate, a post-construction stormwater management ordinance within three (3) years of the effective date of the Permit (i.e., by July 1, 2022). The Order to the Town of Sherborn requires it to enact a post-construction stormwater management ordinance or other regulatory mechanism by September 30, 2025; notify EPA that such an ordinance or regulatory mechanism has become effective within 7 days of its effective date; and provide the Agency with a copy of the regulatory mechanism. The Orders will facilitate the reduction of pollutants found in the permittees' stormwater through the retention or treatment of stormwater after construction on new or redeveloped sites. The Region coordinated with the Massachusetts Department of Environmental Protection (MassDEP) on this matter.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown