← EPA enforcement cases

RICHARDSON HEIGHTS BAPTIST CHURCH AND DALMAC CONSTRUCTION

Administrative - Formal · FY1996 · — · Final Order With Penalty · 36736

$10K
Penalty
Cost recovery
Compliance action

Case

Case Number
06-1996-0449
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (2)

Summary

1. SECTIONS 309(G)(1) AND 309(G)(2) OF THE CLEAN WATER ACT, 33 U.S.C. SECTIONS 1319(G)(1) AND 1319(G)(2). 2. RICHARDSON HEIGHTS BAPTIST CHURCH DALMAC CONSTRUCTION FACILITY: RICHARDSON HEIGHTS BAPTIST CHURCH CONSTRUCTION PROJECT 210 W. RENNNER ROAD RICHARDSON, DALLAS COUNTY, TEXAS 75080 3. RESPONDENT WAS IN VIOLATION OF SECTION 301(A) OF THE CWA BY DISCHARGES OF POLLUTANTS WITHOUT A PERMIT. 4. RELIEF SOUGHT PURSUANT TO SECTION 309(G)(2)(A) OF THE CWA EPA PROPPSES A CIVIL PENALTY OF $10,000 PER VIOLATION, UP TO A MAXIMUM OF $25,000.

Source

Authoritative
EPA ECHO
Machine