# CROWN CENTRAL PETROLEUM CORPORATION
> **Administrative - Formal** · FY1998 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `37744`
- **Case Number:** 06-1998-0047
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** $225K
- **Multimedia (multi-env):** N
## Defendants
- CROWN CENTRAL PETROLEUM CORPORATION (complaint) (settlement)
## Summary

1. SECTION 309(A) OF THE CLEAN WATER ACT ( CWA ), 33 U.S.C.     SECTION 1319(A).                                          2. CROWN CENTRAL PETROLEUM CORPORATION, A MARYLAND CORP.        111 RED BLUFF ROAD                                           PASADENA, HARRIS COUNTY, TEXAS 77251                      3. RESPONDENT WAS IN VIOLATION OF SECTION 301 OF THE CWA BY     DISCHARGING POLLUTANTS FROM THE FACILITY THAT EXCEEDED       PERMITTED EFFLUENT LIMITATIONS ESTABLISHED IN PART I.A.      OF ITS PERMIT, AS SHOWN IN THE CERTIFIED DMRS FILED BY       THE PERMITTEE WITH EPA, AND BY ALLOWING THE BYPASS OF        PROCESS WASTEWATER FROM THE FACILITY IN VIOLATION OF PART    III.B.4.C. OF THE PERMIT.                                 4. RELIEF SOUGHT PURSUANT TO SECTION 309(A) OF THE CWA, EPA     ISSUED AN ADMINISTRATIVE ORDER (AO) ORDERING THE RESPOND-    ENT TO: A) ACCOMPLISH THE FOLLOWING TASKS AND COMPLY WITH    THE FOLLOWING SCHEDULE OF ACTIVITIES: 1) CIVIL FIELD WORK    BY NOV. 30, 1997; 2) PROCUREMENT OF EQUIPMENT BY JAN. 31,    1998; 3) COMPLETION OF CONSTRUCTION BY JUN. 30, 1998; AND    ACHIEVE COMPLIANCE BY JUL. 31, 1998, AND B) REPORT COM-      PLIANCE OR NONCOMPLIANCE WITH THE REQUIREMENTS OF EACH       ACTIVITY NO LATER THAN 14 DAYS FOLLOWING THE DUE DATE OF     EACH ACTIVITY.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*