# BEAU DUNCAN
> **Administrative - Formal** · FY1998 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `37826`
- **Case Number:** 06-1998-0129
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- BEAU DUNCAN (complaint) (settlement)
## Summary

1. SECTION 309(A) OF THE CLEAN WATER ACT ( CWA ), 33 U.S.C.     SECTION 1319(A).                                          2. BEAU DUNCAN                                                  FACILITY: RESIDENTIAL CONSTRUCTION PROJECT                             CONCHO TRAIL OFF WHITE SETTLEMENT ROAD, 8 M W                 OF TEXAS STATE HIGHWAY 820                                  WEATHERFORD, TARRANT COUNTY, TEXAS 76087        3. RESPONDENT WAS IN VIOLATION OF SECTION 301 OF THE CWA BY     FAILING TO MAKE A TIMELY APPLICATION FOR PERMIT COVERAGE     FOR ITS ACTIVITIES AT THE FACILITY, AND WAS NOT COVERED      BY A NPDES PERMIT AT THE RELEVANT TIMES FOR THE RELEVANT     ACTIVITIES.                                               4. RELIEF SOUGHT PURSUANT TO SECTION 309(A) OF THE CWA, EPA     ISSUED AN ADMINISTRATIVE ORDER (AO) ORDERING THE RESPOND-    ENT TO: A) WITHIN 30 DAYS OF THE EFFECTIVE DATE OF THE AO    MAKE A COMPLETE AND CORRECT APPLICATION FOR PERMIT COVER-    AGE AND SUBMIT A COPY OF THE PERMIT APPLICATION, CONFIRM-    ATION OF PERMIT COVERAGE, AND PERMIT NUMBER TO EPA, B)       WITHIN 30 DAYS OF THE AO, TAKE WHATEVER CORRECTIVE ACTION    IS NECESSARY TO CORRECT THE DEFICIENCIES AND ELIMINATE       AND PREVENT RECURRENCE OF THE VIOLATIONS CITED AND TO        COME INTO COMPLIANCE WITH ALL OF THE APP;LICABLE REQUIRE-    MENTS OF THE PERMIT, AND C) WITHIN 30 DAYS OF THE AO,        SUBMIT A COPY OF THE STORM WATER POLLUTION PREVENTION        PLAN (SWPPP) PREPARED AND IMPLEME

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*