1. SECTION 309(A) OF THE CLEAN WATER ACT ( CWA ), 33 U.S.C. SECTION 1319(A). 2. CHRIS BOUZIDEN, DBA SOL AND SONS FEEDYARD WEST OF THE CITY, P.O. BOX 452 ALVA, WOODS COUNTY, OKLAHOMA 73717 3. RESPONDENT WAS IN VIOLATION OF SECTION 301 OF THE CWA BY THE PERMITTEE'S FAILURE TO DEVELOP AND IMPLEMENT AN AP- PROPRIATE POLLUTION PREVENTION PLAN (PPP) BY MAR. 10, 1994, AS REQUIRED. 4. RELIEF SOUGHT PURSUANT TO SECTION 309(A) OF THE CWA, EPA ISSUED AN ADMINISTRATIVE ORDER (AO) TO THE RESPONDENT. THE AO ORDERED THE RESPONDENT TO: A) WITHIN 30 DAYS, TAKE WHATEVER ACTION IS NECESSARY TO DEVELOP AND IMPLEMENTITS PPP, CORRECTTHE INSPECTION DEFICIENCIES, AND MAINTAIN THE PPP AT THE FACILITY, AND B) WITHIN 30 DAYS, SUBMIT A LET- TER TO EPA CERTIFYING THAT THE INSPECTION DEFICIENCIES HAVE BEEN CORRECTED; OR, IF NOT POSSIBLE TO CORRECT THE VIOLATIONS WITHIN 30 DAYS, WITHIN 30 DAYS, SUBMIT A WRIT- TEN PLAN FOR THE COMPLETION AND IMPLEMENTATION OF AN AP- PROPRIATE PPP WITHIN THE SHORTEST REASONABLE TIME, IN- CLUDING A DETAILED DESCRIPTION OF THE SPECIFIC ACTIONS TO BE TAKEN AND A PROPOSED DATE OF COMPLETION AND IMPLEMENT- ATION.