1. SECTION 309(A) OF THE CLEAN WATER ACT ( CWA ), 33 U.S.C. SECTION 1319(A). 2. ASSOCIATED RACK CORPORATION, A FLORIDA CORPORATION, DBA SOUTHWESTERN RACK COMPANY 1401 ROYAL PARKWAY, SUITE A EULESS, TARRANT COUNTY, TEXAS 76040 3. RESPONDENT WAS IN VIOLATION OF SECTION 301 OF THE CWA BY CONDUCTING THE RELEVANT ACTIVITIES AND OPERATING THE FA- CILITY WITHOUT NPDES PERMIT COVERAGE. 4. RELIEF SOUGHT PURSUANT TO SECTION 309(A) OF THE CWA, EPA ISSUED THE RESPONDENT AN ADMINISTRATIVE ORDER (AO). THE AO ORDERED THE RESPONDENT TO: A) WITHIN 30 DAYS, MAKE A COMPLETE AND CORRECT APPLICATION FOR PERMIT COVERAGE, SUBMITTING A COPY OF THE APPLICATION, CONFIRMATION OF COVERAGE, AND THE PERMIT NUMBER TO EPA, B) WITHIN 30 DAYS TAKE WHATEVER CORRECTIVE ACTION IS NECESSARY TO CORRECT THE DEFICIENCIES AND ELIMINATE AND PREVENT RECURRENCE OF THE VIOLATIONS CITED, AND TO COME INTO COMPLIOANCE, C) WITHIN 30 DAYS, SUBMIT A WRITTEN REPORT DETAILING THE SPECIFIC ACTIONS TAKEN TO CORRECT THE VIOLATIONS CITED, EXPLAIN HOW THESE ACTIONS WILL PREVENT RECURRENCE, AND INCLUDE A COPY OF THE FACILITY STORM WATER POLLUTION PRE- VENTION PLAN (SWPPP), D) IF NOT POSSIBLE TO CORRECT THE VIOLATIONS WITHIN 30 DAYS, WITHIN 30 DAYS, SUBMIT A COM- PREHENSIVE PLAN TO DO SO IN THE S