← EPA enforcement cases

PINE CREEK VILLAGE INCORPORATION WATER SYSTEM

Administrative - Formal · FY2000 · — · Unilateral Administrative Order Without Adjudication · 40199

Penalty
Cost recovery
$500
Compliance action

Case

Case Number
06-2000-0580
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

1. SECTION 1414 OF THE SAFE DRINKING WATER ACT ( SDWA ), 42 U.S.C. SECTION 300G-3. 2. PINE CREEK VILLAGE INCORPORATED WATER SYSTEM 833 CLEVELAND GIBBS ROAD ROANOKE, DENTON COUNTY, TEXAS 76262 3. RESPONDENT WAS IN VIOLATION OF SECTION 1414 OF THE SDWA BY: 1) FAILING TO MONITOR FOR LEAD AND COPPER; 2) FAILING TO REPORT THE SPECIFIED INFORMATION WITHIN THE ALLOTTED TIME PERIOD. 4. RELIEF SOUGHT PURSUANT TO SECTION 1414 OF THE SDWA, EPA ISSUED THE RESPONDENT AN ADMINISTRATIVE ORDER (AO) THAT ORDERED THE RESPONDENT TO: 1) WITHIN 60 DAYS, COMPLY WITH LEAD AND COPPER MONITORING REQUIREMENTS; AND 2) COMPLY WITH THE REQUIREMENTS OF 40 CFR SUBPART I (CONTROL OF LEAD AND COPPER).

Source

Authoritative
EPA ECHO
Machine