← EPA enforcement cases

CRUZ CORPORATION, D/B/A/ STAR PAVING COMPANY, AND SANDOVAL C

Administrative - Formal · FY2001 · — · Final Order With Penalty · 41734

$21K
Penalty
Cost recovery
Compliance action

Case

Case Number
06-2001-5189
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (2)

Summary

1. SECTION 309(G) OF THE CLEAN WATER ACT ( SDWA ), 33 U.S.C. SECTION 1319(G). 2. CRUZ CORPORATION, DBA STAR PAVING COMPANY, A NEW MEXICO CORPORATION SANDOVAL COUNTY, A NEW MEXICO COUNTY FACILITY: CAMINO DEL TECOLOTE/CAMINO DE SAN FRANCISCO INTERSTATE 25 EXIT 242, SEVEN MILES EAST ON SR 165, ON THE LEFT PLACITAS, SANDOVAL COUNTY, NEW MEXICO 87043 3. RESPONDENTS WERE IN VIOLATION OF SECTION 301 OF THE CWA BY: 1) FAILING TO PREPARE AND IMPLEMENT A STORM WATER POLLUTION PREVENTION PLAN (SWPPP); 2) THE EROSION AND SEDIMENT CONTROLS WERE NOT PROPERLY INSTALLED AND MAIN- TAINED; 3) SEDIMENT ESCAPED AND OFF-SITE ACCUMULATIONS WERE NOT REMOVED; AND 4) EACH DAY THAT RESPONDENT, CRUZ CORPORATION, CONDUCTED THE RELEVANT ACTIVITIES AND OPERA- TED THE FACILITY WITHOUT NPDES PERMIT COVERAGE FROM ON OR ABOUT JAN. 1, 2000, THROUGH JAN. 13, 2000. 4. RELIEF SOUGHT PURSUANT TO SECTION 309(G) OF THE CWA, EPA PROPOSED A CIVIL PENALTY OF UP TO $27,500 FOR THE VIOLA- TIONS CITED.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown