# TRICON TIMBER, L.L.C., A MONTANA CORPORATION
> **Administrative - Formal** · FY2002 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `41903`
- **Case Number:** 06-2002-1734
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- TRICON TIMBER, L.L.C. (settlement)
## Summary

1. SECTIONS 308(A) AND 309(A) OF THE CLEAN WATER ACT ( CWA )    33 U.S.C. SECTIONS 1318(A) AND 1319(A).                   2. TRICON TIMBER, L.L.C., A MONTANA CORPORATION                 31183 HIGHWAY 64                                             CIMARRON, COLFAX COUNTY, NEW MEXICO 87714                 3. RESPONDENT WAS IN VIOLATION OF SECTION 301 OF THE CWA BY     EACH DAY THAT RESPONDENT CONDUCTED THE RELEVANT ACTIVI-      TIES AND OPERATED THE FACILITY WITHOUT NPDES PERMIT COV-     ERAGE.                                                    4. RELIEF SOUGHT PURSUANT TO SECTIONS 308(A) AND 309(A) OF      THE CWA, EPA ISSUED AN ADMINISTRATIVE ORDER (AO) THAT        ORDERED THE RESPONDENT TO: A) WITHIN 30 DAYS, OBTAIN         NPDES PERMIT COVERAGE, SUBMITTING A COPY OF THE APPLICA-     TION, CONFIRMATION OF COVERAGE AND THE PERMIT NUMBER TO      EPA ALONG WITH A COPY OF THE SWPPP; AND B) WITHIN 45 DAYS    ARRANGE TO MEET WITH EPA AND SHOW CAUSE.

---