# UNIVERSITY OF TEXAS AT TYLER AND RPR CONSTRUCTION INC.
> **Administrative - Formal** · FY2002 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `41950`
- **Case Number:** 06-2002-1781
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- RPR CONSTRUCTION INC. (settlement)
- UNIVERSITY OF TEXAS AT TYLER (settlement)
## Summary

1. SECTIONS 308(A) AND 309(A) OF THE CLEAN WATER ACT ( CWA )    33 U.S.C. SECTION 1318(A) AND 1319(A).                    2. UNIVERSITY OF TEXAS AT TYLER, A TEXAS UNIVERSITY             RPR CONSTRUCTION INC., A TEXAS CORPORATION                   FACILITY: UNIVERSITY OF TEXAS AT TYLER SOCCER FIELD                    3900 UNIVERSITY BOULEVARD                                    TYLER, SMITH COUNTY, TEXAS 75502                3. RESPONDENTS WERE IN VIOLATION OF SECTION 402 OF THE CWA      BY VIOLATING THE TERMS AND CONDITIONS OF THEIR PERMIT.    4. RELIEF SOUGHT PURSUANT TO SECTIONS 308(A) AND 309(A) OF      THE CWA, EPA ISSUED AN ADMINISTRATIVE ORDER (AO) THAT        ORDERED THE RESPONDENT TO: A) OBTAIN NPDES PERMIT COVER-     AGE, SUBMITTING A COPY OF THE APPLICATION, CONFIRMATION      OF COVERAGE AND THE PERMIT NUMBER TO EPA; B) WITHIN 30       DAYS, TAKE CORRECTIVE ACTION TO CORRECT THE DEFICIENCIES     AND ELIMINATE AND PREVENT RECURRENCE OF THE VIOLATIONS       CITED AND TO COME INTO COMPLIANCE; C) WITHIN 30 DAYS,        SUBMIT A WRITTEN REPORT DETAILING THE SPECIFIC ACTIONS       TAKEN AND EXPLAIN HOW THE ACTIONS WILL PREVENT RECUR-        RENCE; D) IF NOT POSSIBLE TO CORRECT THE VIOLATIONS IN 30    DAYS, WITHIN 30 DAYS, SUBMIT A COMPREHENSIVE PLAN TO DO      SO IN THE SHORTEST POSSIBLE TIME; AND E) WITHIN 45 DAYS,     ARRANGE TO MEET WITH EPA AND SHOW CAUSE.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*