# SPRING VALLEY CONSTRUCTION, CONTROL SPECIALIST, INC., SITE C
> **Administrative - Formal** · FY2002 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `41978`
- **Case Number:** 06-2002-1809
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- CONTROL SPECIALIST, INC. (settlement)
- GLENN THURMAN, INC. (settlement)
- HIGHLAND HOMES, LTD. (settlement)
- MHI PARTNERSHIP LTD. (settlement)
- MORRISON HOMES OF TEXAS, INC. (settlement)
- NATGUN CORPORATION (settlement)
- PHOENIX FABRICATORS (settlement)
- SITE CONCRETE, INC. (settlement)
- SPRING VALLEY CONSTRUCTION (settlement)
## Summary

1. SECTIONS 308(A) AND 309(A) OF THE CLEAN WATER ACT ( CWA )    33 U.S.C. SECTIONS 1318(A) AND 1319(A).                   2. SPRING VALLEY CONSTRUCTION, A TEXAS CORPORATION              CONTROL SPECIALIST, INC., A TEXAS CORPORATION                SITE CONCRETE, INC., A TEXAS CORPORATION                     GLENN THURMAN, INC., A TEXAS CORPORATION                     MORRISON HOMES OF TEXAS, INC., A TEXAS CORPORATION           MHI PARTNERSHIP LTD., A TEXAS CORPORATION                    HIGHLAND HOMES, LTD., A TEXAS CORPORATION                    NATGUN CORPORATION, A MASSACHUETTS CORPORATION               PHOENIX FABRICATORS, AN INDIANA CORPORATION                  FACILITY: RAYZOR RANCH DEVELOPMENT                                     LANTANA TRAIL AND RAYZOR ROAD                                DOUBLE OAK, DENTON COUNTY, TEXAS 75067          3. RESPONDENTS WERE IN VIOLATION OF SECTIONS 301 AND 402 OF     THE CWA BY EACH DAY THAT RESPONDENTS CONDUCTED THE RELE-     VANT ACTIVITES AND OPERATED THE FACILITY WITHOUT NPDES       PERMIT COVERAGE AND BY VIOLATING THE TERMS AND CONDITIONS    OF ITS PERMIT.                                            4. RELIEF SOUGHT PURSUANT TO SECTIONS 308(A) AND 309(A) OF      THE CWA, EPA ISSUED AN ADMINSTRATIVE ORDER (AO) THAT         ORDERED THE RESPONDENTS TO: A) WITHIN 30 DAYS, OBTAIN        NPDES PERMIT COVERAGE, SUBMITTING A COPY OF THE APPLICA-     TION, CONFIRMATION OF COVERAGE AND THE PERMIT NUMBER TO      EPA; B) WITHIN 30 DAYS, TAKE CORR

---