# ENERGY COATINGS COMPANY D/B/A ENCOAT
> **Administrative - Formal** · FY1988 · — · Final Order With Penalty
## Case
- **Activity ID:** `48155`
- **Case Number:** 08-1988-0018
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $26K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- ENCOAT-NORTH ARLINGTON, INC. (complaint) (settlement)
- ENERGY COATINGS COMPANY D/B/A ENCOAT (complaint) (settlement)
## Summary

-FAILURE TO MAKE A TIMELY DETERMINATION OF WHETHER ITS    SOLID WASTES WERE HAZARDOUS WASTES.                             -STORAGE OF HAZARDOUS WASTE AT THE GRANGER FACILITY FOR   LONGER THAN 90 DAYS AND/OR 270 DAYS WITHOUT A PERMIT OR      INTERIM STATUS.

---