# HURON, CITY OF
> **Administrative - Formal** · FY1990 · — · —
## Case
- **Activity ID:** `48567`
- **Case Number:** 08-1990-0032
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** —
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- HURON, CITY OF (complaint)
## Summary

FAILURE TO COMPLY WITH COMPLIANCE SCHEDULE FOR             CONSTRUCTION OF NEW OR UPGRADED FACILITIES BY 1 NOV 1985.      FAILURE TO BEGIN CONSTRUCTION OF IMPROVEMENTS TO ITS       SEQUENCING BATCH REACTOR FACILITIES BY 1 APR 1989 UNDER AO   88-22-C, AUG 23, 1988.                                         FAILURE TO BEGIN CONSTRUCTION OF NEW OR UPGRADED           FACILITIES TO MEET ITS PERMIT FINAL EFFLUENT LIMITS NO LATER THAN JUL 1, 1989.

---