← EPA enforcement cases

TOOELE ARMY DEPOT - NORTH AREA

Administrative - Formal · FY1991 · — · — · 48990

Penalty
Cost recovery
Compliance action

Case

Case Number
08-1991-0222
Type
Administrative - Formal
Lead
EPA
Outcome
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

SPECIAL NOTICE LETTER SENT 05/01/91. TRIGGERING 90-DAY NEGOTIATION PERIOD FOR FEDERAL FACILITIES AGREEMENT (FFA OR IAG) PURSUANT TO CERCLA SECTION 120. ACCORDING TO POLICY 30 DAYS MORE ARE ALLOWED TO COMPLETE NEGOTIATIONS IF SUBSTANTIAL AGREEMENT IS REACHED IN THE 90 DAYS, AND FINAL AGREEMENT WAS REACHED IN 90 DAYS, AND FINAL AGREEMENT WAS REACHED WITHIN THE 120 DAYS. SIGNATURES OBTAINED 09/16/91 ( FFA EFFECTIVE).