# JOHNSON, WARREN/JOHNSON BERNICE M/ ED RUTTEN CONSTRUCTION
> **Administrative - Formal** · FY1993 · — · Final Order With Penalty
## Case
- **Activity ID:** `49646`
- **Case Number:** 08-1993-0204
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $75K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- ED RUTTEN CONSTRUCTION (complaint) (settlement)
- JOHNSON, BERNICE M (ESTATE) (complaint) (settlement)
- JOHNSON, WARREN R (complaint) (settlement)
## Summary

THIS IS A 10 COUNT COMPLAINT AND NOTICE OF OPPORTUNITY FOR   HEARING FOR VIOLATIONS OF THE CLEAN AIR ACT AND NESHAP'S.    THE PROPOSED CIVIL PENALTY IS $158,800.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*