← EPA enforcement cases

EQUUS FARMS

Administrative - Formal · FY1999 · — · — · 51149

Penalty
Cost recovery
Compliance action

Case

Case Number
08-1999-0025
Type
Administrative - Formal
Lead
EPA
Outcome
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

THIS ADMINISTRATIVE ORDER IS AN ORDER FOR COMPLIANCE. EQUUS IS ORDERED TO IMPLEMENT THE RESTORATION AND MITIGATION PLAN FOR OLD HOLES 2, 8, & 9 OF THE GOLF COURSE OWNED BY EQUUS FARMS WITH THE EXCEPTION OF THAT PORTION PERTAINING TO THE 2.67 ACRE COMPENSATORY MITIGATION SITE WITHIN 90 DAYS AFTER EFFECTIVE DATE OF THIS ORDER. NO LATER THAN 180 DAYS AFTER THE EFFECTIVE DATE OF THIS ORDER, EQUUS SHALL IMPLEMENT THE 2.67 ACRE COMPENSATORY MITIGATION SITE PORTION OF THE RESTORATION PLAN.