# PACIFIC AMERICAN ASBESTOS CONTROL CORPORATION
> **Judicial** · FY1990 · — · Final Order With Penalty
## Case
- **Activity ID:** `52200`
- **Case Number:** 09-1990-0013
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $22K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- PACIFIC AMERICAN ASBESTOS CONTROL CORP. (complaint) (settlement)
## Summary

ROSEVILLE COMMUNITY HOSPITAL HIRED THE DEFENDANT, PACIFIC  AMERICAN ASBESTOS CONTROL CORPORATION ( PACIFIC ) TO         REMOVE INSULATION MATERIAL FROM THE HOSPITAL'S BOILER ROOM.  AN EPA INSPECTOR DISCOVERED THAT IN THE COURSE OF THIS       RENOVATION PROJECT, THE DEFENDANT FAILED TO KEEP FRIABLE     ASBESTOS MATERIALS ADEQUATELY WET UNTIL COLLECTED FOR        DISPOSAL.  SUBSEQUENTLY, EPA DISCOVERED THAT THE DEFENDANT'S NOTIFICATION REGARDING THIS JOB FAILED TO REPORT PROPERLY    THE APPROXIMATE AMOUNT OF FRIABLE ASBESTOS PRESENT IN THE    FACILITY.  THESE ACTIONS CONSTITUTED VIOLATIONS OF THE       NOTIFICATION AND WORK PRACTICE REQUIREMENTS SET FORTH IN     40. C.F.R. PART 61, SUBPART M.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*