# SAN MATEO CREEK BRIDGE
> **Administrative - Formal** · FY1998 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `52981`
- **Case Number:** 09-1998-0105
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- SAN MATEO COUNTY TRANSIT DISTRICT (complaint) (settlement)
## Summary

THIS IS A UNILATERAL ADMINISTRATIVE ORDER PURSUANT TO        SECTION 309A OF THE CWA, ISSUED AGAINST THE SAN MATEO        COUNTY TRANSIT DISTRICT FOR WORK PERFORMED AT SAN MATEO      CREEK BRIDGE IN VIOLATION OF CWA SECTION 404 (WETLANDS).     THE ORDER REQUIRES THE COUNTY TO UNDERTAKE RESTORATION       OF THE SITE TO PRE-DISTURBED CONDITIONS, MEANING THAT THE    AREA WILL BE ABLE SUPPORT CREEK HABITAT FOR THE TIDE         WATER GOBY, AN ENDANGERED FISH SPECIES.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*