# MORTON FRIEDMAN - SCHMITT CONSTRUCTION
> **Administrative - Formal** · FY1999 · — · Final Order With Penalty
## Case
- **Activity ID:** `53223`
- **Case Number:** 09-1999-0161
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- MORTON FRIEDMAN (complaint) (settlement)
- SCHMITT CONSTRUCTION (complaint) (settlement)
## Summary

THIS IS AN ADMIN PENALTY CASE UNDER THE CLEAN AIR            ACT AGAINST THE PROPERTY OWNER MORTON FRIEDMAN AND A         CONTRACTOR SCHMITT CONSTRUCTION FOR IMPROPER DEMOLITION      AND RENOVATION AT A SITE REQUIRING ASBESTOS REMOVAL.         THE RESPONDENTS FAILED TO PROVIDE NOTICE PRIOR TO THE        REMOVAL WORK, FAILED TO KEEP THE ASBESTOS WET DURING         THE REMOVAL, AND FAILED TO MAINTAIN A WASTE SHIPMENT         RECORD AFTER THE REMOVAL.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*