# GENERAL ELECTRIC CO.
> **Judicial** · FY1995 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `5468`
- **Case Number:** 02-1995-0269
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** $960K
- **Compliance action $:** $300K
- **Multimedia (multi-env):** N
## Defendants
- ADVANCED NUCLEAR FUELS INC
- CURTISS-WRIGHT CORP (complaint) (settlement)
- DEPT OF DEFENSE
- GENERAL ELECTRIC COMPANY (complaint) (settlement)
- MECHANICAL TECHNOLOGY INC (complaint) (settlement)
- NYS ENERGY RESEARCH & DEVELOPMENT AUTHOR (complaint) (settlement)
- OLIN CORP (complaint) (settlement)
- POWER TECHNOLOGIES INC (complaint) (settlement)
- WRIGHT MALTA CORP (complaint) (settlement)
## Summary

PRN - REPORT SENT ON SEPTEMBER 29, 1995.  THE REPORT IS    INTENDED TO PREPARE EPA AND THE DOJ FOR THE COMMENCEMENT OF  NEGOTIATIONS PURSUANT TO CERCLA, BETWEEN THE U.S. AND THE    PRPS AT THE SITE.  AMONG THE PRPS TO BE INVOLVEDIN THE       NEGOTIATIONS IS THE DOD.  EPA EXPECTS TO BEGIN NEGOTIATING   A CONSENT DECREE WITH THE PRPS DURING THE COMING WINTER FOR  THE PERFORMANCE OF REMEDIAL DESIGN AND REMEDIAL ACTION AND   FOR RECOVERY OF EPA'S PAST COSTS.                            *THERE ARE NINE (9) PROPOSED DEFENDANTS (PRPS)               FACILITY NAME:  MALTA ROCKET FUEL AREA SITE                  ADDRESS:        PLAINS RD, MALTA, NY 12020                   09/29/95 - PRN PACKAGE SENT TO DOJ.                          09/22/97 - REFERRED PRN CD FOR SIGNATURE AND ENTRY.          *                                                            01/05/98 - COMPLAINT FILED& CD LODGED(7 DEF'S NAMED IN COMP) *                                                            03/16/98 - CD ENTERED

---