# EATON CORPORATION
> **Administrative - Formal** · FY1995 · — · Final Order No Penalty
## Case
- **Activity ID:** `5511`
- **Case Number:** 02-1995-0315
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** $300K
- **Multimedia (multi-env):** N
## Defendants
- BATAVIA, CITY OF (complaint) (settlement)
- BATAVIA, TOWN OF (complaint) (settlement)
- EATON CORP (complaint) (settlement)
- GTE PRODUCTS CORP (complaint) (settlement)
- NL INDUSTRIES INC (complaint) (settlement)
- R.E. CHAPIN MANUFACTURING WORKS INC (complaint) (settlement)
- UNISYS CORP (complaint) (settlement)
## Summary

ORDER ON CONSENT FOR REMEDIAL DESIGN. AMENDMENTS TO ORDER ISSUED 12/7/95: ADD 2 RESPONDENTS; THERE ARE NOW (7) RESPONDENTS NAMED.

---