Summary

THIS 167 ORDER MEMORIALIZES AN AGREEMENT BETWEEN EPA AND RESPONDENT, IN WHICH RESPONDENT AGREES TO OBTAIN A PSD PERMIT REVISION REQUIRING INSTALLATION OF SELECTIVE CATALYTIC REDUCTION (SCR) AND TO INSTALL SCR, PRIOR TO COMMENCEMENT OF COMMERCIAL OPERATION.