# SAN FRANCISCO MUNICIPAL RAILWAY
> **Administrative - Formal** · FY1998 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `57300`
- **Case Number:** HQ-1998-0007
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- SAN FRANCISCO MUNICIPAL RAILWAY (complaint) (settlement)
## Summary

09/22/98                                                     THIS IS AN URBAN BUS REBUILD CASE IN WHICH THE RESPONDENT    SELF-REPORTED 15 VIOLATIONS. IT HAD REBUILT 15 BUSES         WITHOUT THE PROPER CERTIFIED REBUILD EQUIPMENT. RESPONDENT   HAS AGREED TO A TIMETABLE TO PUT THE BUSES INTO COMPLIANCE,  AND TO REPORT TO EPA WITH COMPLIANCE STATUS REPORTS.

---