FEFDERAL FACILITY AGREEMENT: FORT DEVENS  #MA7210025154

FY2015: OU FORMER FORT DEVENS ARMY INSTALLATION AOC72/SA71:  The selected remedy based on current conditions at AOC72 Plow Shop Pond is No Further Action.  The selected remedy for SA71 Former Railroad Roundhouse is Limited Action: Implementation of Land Use Controls (LUCs).  The LUCs are addressed through institutional controls, access restrictions, affirmative measures, and prohibitive directives.  Annual site inspections of the site to evaluate access controls and evaluate the overall effectiveness of the LUCs will be conducted every five years.

FY 2014:   OU1 Land Use Controls. 
FY 2014:   OU12 Pre-construction UXO/MED clearance and Land Use Controls

---