← EPA enforcement cases

PACE DEVELOPMENT GROUP, INC. (WHITEHALL PLANTATION S/D)

Administrative - Formal · FY2006 · — · Final Order With Penalty · 600010291

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2006-4517
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (2)

Summary

9/27/06 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $25,000. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ORDER ALLEGES: DURING THE CSWEI, EPA REGION 4 ALLEGES THAT RESPONDENT DISCHARGED STORM ASSOCIATED WITH INDUSTRIAL ACTIVITY FROM ITS SITE WITHIN THE MEANING OF CWA SECTION 402. DURING THE CSWEI, EPA INSPECOTS ALLEGED THE FOLLOWING: A. SILT FENCING ALONG THE UTILITY EASEMENT ON THE SOUTERN PORTION OF THE SITE WAS IN NEED OF MAINTENANCE, B. DETENTION PONDS #4 AND #7 WERE IN NEED OF MAINTENANCE. RESPONDENT FAILED TO COMPLY WITH PART VI.N OF THE PERMIT. IN VIOLATION OF CWA SECTIONS 301 AND 402.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown