# HEATHERWOOD DEVELOPERS, INC.
> **Administrative - Formal** · FY2006 · — · Final Order With Penalty
## Case
- **Activity ID:** `600011090`
- **Case Number:** 04-2006-5507
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- HEATHERWOOD DEVELOPERS, INC. (SB) (complaint) (settlement)
## Summary

9/29/06 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $50,000.  RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS.  ORDER ALLEGES:  COMMENCING ON OR ABOUT MARCH 24, 2005, TO THE PRESENT, RESPONDENT, OR THOSE ACTING ON BEHALF OF RESPONDENT, DISCHARGED DREDGED AND/OR FILL MATERIAL INTO WATER OF THE UNTIED STATES ON THE SITE USING EARTH MOVING MACHINERY, DURING UNAUTHORIZED ACTIVITIES ASSOCIATED WITH THE CONSTRUCTION OF A STORM WATER DETENTIION FACILITY FOR A RESIDENTIAL DEVELOPMENT.  RESPONDENT DISCHARGES WERE WITHOUT A PERMIT FOR STORMWATER DETENTION SITES D OR D1 UNDER SECTION 404 OF THE CWA.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*