# M A MORTENSON
> **Administrative - Formal** · FY2007 · — · Final Order With Penalty
## Case
- **Activity ID:** `600022084`
- **Case Number:** 01-2007-2018
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- M A MORTENSON (complaint) (settlement)
- PETTINI CONTACTING CORP (SB) (complaint)
## Summary

ON AUGUST 2, 2006, EPA CONDUCTED A NPDES CONSTRUCTION STORM WATER INSPECTION OF THE SITE AS A PART OF A MULTI-MEDIA INSPECTION OF THE SUB BASE. THE INSPECTION REVEALED THAT MORTENSON AND PETTINI VIOLATED PROVIDSIONS OF THE STATE OF CONNECTICUT'S 2004  GENERAL PERMIT FOR THE DISCHARGE OF STORMWATER AND DEWAERING WASTEWATERS FROM CONSTRUCTION ACTIVITIES  (CT CGP) BY: (1) FAILING TO CONDUCG AND/OR DOCUMENT STORM WATERS INSPECTIONS; (2) FAILING TO IMPLEMENT AND/OR MAINTAIN STORM WATER CONTROLS REQUIRED BY THE SITE'S STORMWATER POLLUTION CONTROL PLAN (SPCP); AND (3) AILING TO UPDATE OR AMEND THE SPCP AS NEEDED.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*