# Triangle Exxon
> **Administrative - Formal** · FY2007 · — · Final Order With Penalty
## Case
- **Activity ID:** `600030609`
- **Case Number:** 02-2007-7930
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Triangle Exxon (SB) (complaint) (settlement)
## Summary

This was one of several facilities inspected in NJ in fulfillment of the USTCA inspection requirement.  The facility was issued Field Citation II-UST-FC-1151, in the amount of $750, for the following violations:  280.21(d):  failure to provide overfill prevention for an existing tank; 280.41(a):  failure to monitor tanks at least every 30 days;  and 280.44(a):  failure to conduct annual test of the automatic line leak detectors.

---