← EPA enforcement cases

TENNESSEE AMERICAN WATER (CITICO WATER TREATMENT PLANT)

Administrative - Formal · FY2007 · — · Final Order With Penalty · 600040929

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2007-8009
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

4/10/07 - EXPEDITED SETTLEMENT AGREEMENT ISSUED, ASSESSING A PENALTY OF $2,160, DUE WITHIN 15 DAYS. ALLEGED VIOLATIONS: RESPONDENT DID NOT PROVIDE EVIDENCE THAT IT HAS RETAINED ALL PROCESS HAZARD ANALYSES FOR THE LIFE OF THE COVERED PROCESS AS REQUIRED BY 40 CFR 68.67(g); RESPONDENT DID NOT PROVIDE EVIDENCE THAT IT HAS DEVELOPED AND IMPLEMENTED WRITTEN OPERATING PROCEDURES THAT ADDRESS THE FOLLOWING ELEMENTS FOUND AT 40 CFR 68.69(a): OPERATING LIMITS, INCLUDING (2)(i) CONSEQUENCES OF DEVIATION AND (2)(ii) STEPS REQUIRED TO CORRECT OR AVOID DEVIATION, SAFETY AND HEALTH CONSIDERATION, INCLUDING (3)(i) PROPERTIES OF, AND HAZARDS PRESENTED BY, THE CHEMICALS USED IN THE PROCESS, AND (3)(iii) CONTROL MEASURES TO BE TAKEN IF PHYSICAL CONTACT OR AIRBORNE EXPOSURE OCCURS; RESPONDENT DID NOT PROVIDE EVIDENCE THAT IT HAS ANNUALLY CERTIFIED THE OPERATING PROCEDURES (I.E., THAT THE PROCEDURES ARE CURRENT AND ACCURATE) ON AN ANNUAL BASIS AS REQUIRED BY 40 CFR 68.69(c); AND RESPONDENT DID NOT PROVIDE EVIDENCE THAT AT LEAST EVERY 3 YRS, RESPONDENT HAS EVALUATED ITS COMPLIANCE WITH THE PREVENTION PROGRAM REQUIREMENTS AND CERTIFIED THAT ITS PROCEDURES AND PRACTICES ARE ADEQUATE AND ARE BEING FOLLOWED AS REQUIRED BY 40 CFR 68.79(a).

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown