PREMCOR REFINING GROUP/VALERO ENERGY CO (NATIONAL CASE)

Judicial · FY2007 · — · Final Order With Penalty · 600048695

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2007-9017
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
DOJ Docket
90-5-2-1-06811/1
Multimedia
Self-disclosure
N

Defendants (2)

Summary

PREMCOR HAS VIOLATED THE FOLLOWING REGS: PSD/NSR REGULATIONS - FAILURE TO APPLY FOR AND OBTAIN APPROPRIATE PERMITS MODIFYING, AND CONSTRUCTING AND/OR RECONSTRUCTING PROCESS HEATERS AND BOILERS, AND FLUIDIZED CATALYTIC CRACKING UNITS (FCCs); NSPS SUBPART A AND J REGULATIONS - FAILURE TO COMPLY WITH THE EMISSION LIMITS, MONITORING REQUIREMENTS FOR FLARING DEVICES, FCCUs, HEATERS AND BOILERS, AND TO OPERATE AND MAINTAIN THEIR HEATERS, BOILERS AND FLARING DEVICES IN A MANNER CONSISTENT WITH GOOD AIR POLLUTION CONTROL PRACTICES; LDAR REGULATIONS (NSPS SUBPART GGG AND NESHAP PART 63, SUBPARTS H AND CC) - FAILURE TO TEST AND REPAIR EQUIPMENT (PUMPS, VALVES AND COMPRESSORS); AND BWON (NESHAP FOR BENZENE WASTE OPERATIONS AS IMPLEMENTED AT 40 CFR PART 61, SUBPART FF) REGULATIONS - FAILURE TO TREAT AND CONTROL, AND INCLUDE ALL WASTE STREAMS IN THEIR TOTAL ANNUAL BENZENE (TAB) QUANTITY.

Source

Authoritative
EPA ECHO
Machine