← EPA enforcement cases

BELPORT - 2

Administrative - Formal · FY2007 · — · Unilateral Administrative Order Without Adjudication · 600050017

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2007-1135
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

VIOLATIONS: ENVIRONMENTAL PROTECTION AGENCY (EPA) REGULATIONS REQUIRE THE OWNER OR OPERATOR OF AN INJECTION WELL TO COMPLETE PLUGGING WITHIN ONE YEAR AFTER TERMINATION OF INJECTION OPERATIONS. RESPONDENT VIOLATED OSAGE UNDERGROUND INJECTION CONTROL REGULATIONS BY FAILING TO PLUG TWO INJECTION WELLS AS REQUIRED. REMEDY: PLUG ONE INJECTION WELL WHICH IS ON A LEASE TERMINATED BY THE BIA. THE OTHER WELL MUST BE EITHER PLUGGED OR CONVERTED TO PRODUCTION OR RESPONDENT MUST PROVIDE A PLAN FOR FUTURE USE TO THE EPA BY OCTOBER 1, 2007. PENALTY: NONE