# WELDON - 2
> **Administrative - Formal** · FY2007 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `600050049`
- **Case Number:** 06-2007-1136
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- WELDON CORPORATION (complaint) (settlement)
## Summary

VIOLATIONS:	ENVIRONMENTAL PROTECTION AGENCY (EPA) REGULATIONS REQUIRE THE OWNER OR OPERATOR OF AN INJECTION WELL TO PLUG THE WELL ACCORDING TO EPA REGULATIONS WITHIN ONE YEAR AFTER TERMINATION OF INJECTION OPERATIONS.  RESPONDENT VIOLATED OSAGE UNDERGROUND INJECTION CONTROL REGULATIONS BY FAILING TO PLUG FIVE INJECTION WELLS WITHIN ONE YEAR AFTER TERMINATION OF INJECTION OPERATIONS.

REMEDY:	PLUG THE FIVE INJECTION WELLS BY OCTOBER 1, 2007.

PENALTY:	NONE

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*