# NEWPORT NAVY BASE
> **Administrative - Formal** · FY2008 · — · Final Order No Penalty
## Case
- **Activity ID:** `600079429`
- **Case Number:** 01-2008-1028
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- NEWPORT NAVY BASE (settlement)
## Summary

ON JULY 24, 2007, EPA RECEIVED A RENOVATION NOTIFICATION FROM U.S NAVAL STATION-NEWPORT VIA U.S.MAIL. THE NOTIFICATION WAS DATED JULY 19, 2007 AND THE RENOVATION START DATE WAS JULY 1, 2007. THE NOTIFICATION WAS NOT GIVEN TO EPA AT LEAST 10 WORKING DAYS BEFORE THE ASBESTOS STRIPPING OR REMOVAL WORK OR ANY OTHER ACTIVITY BEGAN, WHICH IS IN VIOLATION OF THE ASBESTOS NESHAP. THE COMPLIANCE ORDER ENSURES THAT NAVSTA NEWPORT TAKES IMMEDIATE STEPS TO CONDUCT BUSINESS IN FULL COMPLIANCE WITH THE ASBESTOS NESHAP.

---