# Professional Center
> **Administrative - Formal** · FY2008 · — · Final Order With Penalty
## Case
- **Activity ID:** `600088136`
- **Case Number:** 02-2008-8403
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- George Blackhall (complaint)
- Professional Center (complaint) (settlement)
## Summary

System failed to comply with a previously issued AO, ordering Respondent to submit radionuclides monitoring results (or historical data) within 45 days of the receipt of the AO.  AO was received by Respondent on October 30, 2007 and information was due on December 14, 2007.

---