THIS IS A FEDERAL FACILITY AGREEMENT FOR FORT EUSTIS, A 9,000 ACRE ARMY GARRISON THAT WAS LISTED ON THE NPL IN 1994. THE AGREEMENT PROVIDES PROCEDURES AND SCHEDULES FOR COMPLETING RI/FS, RD/RA AND REMOVAL ACTIONS UNDER CERCLA. AT THE TIME OF SIGNING, THIRTEEEN OPERALBE UNITS WERE IDENTIFIED. IN ADDITION, SEVERAL MUNITIONS RESPONSE PROGRAM SITES MAY BE INVESTIGATED AND CLEANED UP UNDER THE AGREEMENT.
02/15/2018 ROD for LF001: LF001, a former landfill, encompasses approximately 3 acres; operated from at least 1937 until 1953; and was covered with earthen material in the early 1960s. The USAF and EPA, in consultation with VDEQ selected the remedy - Additional Soil Cover, Land Use Controls and Groundwater Monitoring. This remedy will control exposure to landfill contents and demonstrate continued protection of human health and the environment.
05/18/2018 ESD for Bailey Creek (OU-01): The modification to the remedy was necessary to address areas of contamination in the outfall, identified during remedy implementation, which could not achieve the remediation goal. The ESD modifies the ROD by substituting a combination of excavation and capping with geotextile fabric in the drainage swale in lieu of the original remedy of sediment excavation to achieve protection of human health and the environment. In addition, because some areas of the drainage swale will contain sediment with contaminant concentrations above the remediation goal, this ESD includes a thorough description