# ACME ABATEMENT CONTRACTOR
> **Administrative - Formal** · FY2008 · — · Final Order No Penalty
## Case
- **Activity ID:** `600092301`
- **Case Number:** 01-2008-1505
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- ACME ABATEMENT CONTRACTOR INC (SB) (settlement)
## Summary

In March 2008, Acme Abatement Contactor, Inc. of Seekonk, MA began asbestos abatement work at the Former St. James Cheuch located in West Warwick, RI.  Acme Abatement Contractor, Inc. did not submit a renovation and demolition notification to EPA at least 10 working days before the asbestos stripping or removal work or any other activity began, which is in violation of Asbestos National Emission Standards for Hazardous Air Pollutants (NESHAP).  On April 16, 2008, the Region issued an Immediate Compliance Order to ensure that Acme Abatement Contactor, Inc. take immediate steps to conduct business in full compliance with the Asbestos NESHAP.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*