← EPA enforcement cases

ALCAS CUTLERY CORPORATION, ET.AL.

Judicial · FY1997 · — · Final Order With Specified Cost Recovery · 6269

Penalty
$350K
Cost recovery
$840K
Compliance action

Case

Case Number
02-1997-0366
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
DOJ Docket
90-11-2-181B
Multimedia
N
Self-disclosure
N

Defendants (2)

Summary

THIS CONSENT DECREE REQUIRES ALCAS CUTLERY CORP. AND ALCOA TO PERFORM THE RD/RA SELECTED IN THE OU2 ROD FOR THE OLEAN WELLFIELD SITE, FOR THE ALCAS PROPERTY WHICH IS PART OF THE OLEAN WELLFIELD SITE. THE CONSENT DECREE ALSO REQUIRES THE SETTLING DEFENDANTS TO REIMBURSE THE UNITED STATES FOR PAST RESPONSE COSTS, OVERSIGHT COSTS, PAY OTHER FUTURE RESPONSE COSTS ASSOCIATED WITH ITS PROPERTY, PAY 1/4 OF ALL THE FUTURE RESPONSE COSTS ASSOCIATED WITH THE SITE THAT ARE NOT ASSOCIATED WITH ITS PROPERTY OR THREE OTHER PROPERTIES IDENTIFIED AS SOURCES OF CONTAMINATION TO THE AQUIFER.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown