← EPA enforcement cases

Hydro-Systems, Inc. and Sivage-Thomas Homes

Administrative - Formal · FY2002 · — · Unilateral Administrative Order Without Adjudication · 84597

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2002-1848
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (2)

Summary

'**VIOLATION: 1) Respondent Sivage-Thomas Homes conducted the relevant activites and operated the facility without NPDES permit coverage and respondent hydro-Systems, inc. violated the conditions of its permit. **RELIEF SOUGHT: a) Within 30 days, respondent Sivage-thomas will obtain NPDES permit coverage; b) Within 30 days, respondent Hydro-Systems, Inc. shall take corrective action; c) Within 30 days, report on the actions taken; d) If unable to correct the violations in 30 days, within 30 days, submit a comprehensive plan to do so; and e) Within 45 days, arrange to meet with EPA and show cause

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown